Erer Dam & Irrigation Development Project Summary
Project Overview
The Erer Dam and Irrigation Development Project is a major infrastructure initiative in Ethiopia designed to provide water for irrigation and other uses. The final design report covers dam appurtenant structures including the spillway and outlet works.
Key Project Details:
- Location: Ethiopia
- Client: Ministry of Water Resources, Federal Democratic Republic of Ethiopia
- Consultant: Concert Engineering and Consulting Enterprise (CECE) in association with Consulting Engineering Service
- Report Date: May 2009
- Design Standards: International standards and Ethiopian design standards where appropriate
Main Structures
1. Irrigation Outlet Works
The outlet works are designed to regulate and release water for irrigation and environmental flows.
Component | Description |
---|---|
Design Capacity | 3.05 m³/sec (3.0 for irrigation + 0.05 for environmental flows) |
Intake Structure | High-level dry intake tower with three multilevel entry ports (sill levels at 1370m, 1373.82m, 1377.64m) |
Conduit | 123m long, 1.1m × 1.1m reinforced concrete rectangular conduit |
Control System | Four control gates (three service, one emergency) operated from intake tower |
Terminal Structure | USBR stilling basin Type III (8.6m long) for energy dissipation |
2. Spillway Structure
Located on the left abutment, designed to safely pass flood flows.
Component | Description |
---|---|
Type | Ungated free overflow ogee crested spillway |
Design Discharge | 441 m³/sec |
Crest Length | 30 meters |
Chute | 590m long with varying width (30m to 20m) and slope |
Energy Dissipator | USBR stilling basin Type III (21m long) with chute blocks, baffle blocks, and end sill |
Key Design Features
Hydraulic Design
- Spillway crest profile designed using USBR standard equations
- Supercritical flow maintained throughout spillway chute
- Hydraulic jump analysis for energy dissipation
- Tailwater analysis to ensure proper jump formation
- Riprap protection for exit channel (1.5m thickness)
Structural Design
- Reinforced concrete structures using Grade C30 concrete
- RB400 grade reinforcement (400N/mm² yield strength)
- 50mm minimum cover for water/earth contact structures
- Finite element analysis using SAP 2000 software
- Pile foundation for intake tower (3.4m diameter base)
Construction Quantities and Costs
Item | Quantity | Unit | Cost (Birr) |
---|---|---|---|
Irrigation Outlet Works | |||
Excavation | 3,376 | m³ | 54,117 |
Concrete (C30) | 900 | m³ | 995,112 |
Gates (4 units) | 36 | m² | 1,080,000 |
Subtotal | 2,729,798 Birr | ||
Spillway Works | |||
Excavation | 71,520 | m³ | 1,146,466 |
Concrete (C30) | 23,524 | m³ | 26,010,016 |
Stone Masonry | 2,800 | m³ | 1,113,532 |
Subtotal | 32,038,253 Birr |
Construction Schedule
The estimated construction period is 12 calendar months, with major activities including:
- Excavation and backfill
- Concrete works with formwork
- Installation of gates and metal works
- Channel protection works
Key Considerations
- High sediment load in catchment area influenced intake design (high-level, multi-level entry ports)
- No bottom outlet provided - complete reservoir evacuation not possible
- Spillway designed for reliability in remote location (ungated, simple operation)
- Structural designs account for seismic activity (Zone 1 with 0.03g ground acceleration)
- Emphasis on crack control in concrete structures