Erer Dam & Irrigation Development Project - Final Design Summary
Project Overview
The Erer Dam is a major storage dam across the Erer River in Ethiopia, designed primarily for irrigation development. The project includes:
- A 36.6m high zoned earthfill dam (1460m long)
- Irrigation outlet with intake tower
- Chute spillway with ogee crest
- River diversion works
Key Design Parameters
Parameter | Value |
---|---|
Dam Type | Zoned Earthfill Dam (selected due to seismic conditions and foundation characteristics) |
Location | 6km upstream of Harar-Jijiga road bridge, 25km from Harar |
Seismic Zone | Zone IV (horizontal seismic coefficient = 0.15) |
Diversion Design Flood | 50-year return period (151 m³/s) |
Reservoir Levels
Level | Elevation (m) | Description |
---|---|---|
Dam Crest | 1384.6 | Top of embankment with 1m parapet wall |
Maximum Water Level (MWL) | 1382.6 | For PMF condition |
Full Reservoir Level (FRL) | 1379.0 | Normal operating level |
Minimum Draw Down Level | 1371.0 | Below irrigation outlet centerline |
Dead Storage Level | 1369.85 | After 50 years sedimentation |
Dam Components
- Crest: 9m width with 36.6cm camber
- Core: Central clay core (5m top width, slopes 1H:1V)
- Shell Zones: Sandy gravel material (upstream and downstream)
- Slope Protection:
- Upstream: 1m thick dumped rock riprap with filter blanket
- Downstream: 30cm stone pitching
- Filters: Transition and horizontal filters to control seepage
- Foundation Treatment: Cutoff trench (4m deep in riverbed), plastic concrete diaphragm wall
Stability Analysis Results
Loading Condition | Factor of Safety | Minimum Required |
---|---|---|
End of Construction (U/S) | 2.075 | 1.0 |
End of Construction (D/S) | 1.475 | 1.0 |
Sudden Drawdown (U/S) | 1.814 | 1.3 |
Steady Seepage (D/S) | 1.509 | 1.5 |
Earthquake Condition | 1.009-1.051 | 1.0 |
Construction Schedule
The project has a tentative construction period of 36 months, with key activities including:
- Site preparation and foundation treatment
- Embankment construction with diversion channel
- Spillway and outlet works construction
- Final closure of diversion gap
Instrumentation
The dam will be equipped with monitoring instruments including:
- Vibrating wire piezometers (50 total)
- Inclinometers (4 nos.)
- Surface settlement points