Dabus Hydropower Project Pre-Feasibility Study Summary
Project Overview
The Dabus Hydropower Project involves the development of a cascade system along the Dabus River in Ethiopia, consisting of two main plants:
Key Project Components
- Dabus ch-130: 304 MW capacity, 1,293 GWh/year production
- Dabus ch-108: 494 MW capacity, 2,140 GWh/year production
- Transmission system connecting to Ethiopian grid
- Total investment with significant economic returns
Technical Specifications
Dabus ch-130 Plant
Feature | Specification |
---|---|
Dam Type | RCC Gravity Dam (55m height, 1,610m length) |
Reservoir Capacity | 2,470 Mm³ (live storage: 2,335 Mm³) |
Waterways | 5.5km tunnel, 16m diameter surge shaft, 2.1km penstocks |
Turbines | 2 × 152 MW Francis turbines |
Dabus ch-108 Plant
Feature | Specification |
---|---|
Dam Type | RCC Gravity Dam (82m height, 444m length) |
Reservoir Capacity | 53 Mm³ (live storage: 18 Mm³) |
Waterways | 6.2km tunnel, 16m diameter surge shaft, 970m penstocks |
Turbines | 2 × 247 MW Francis turbines |
Key Studies and Findings
Topography
Comprehensive surveys conducted using:
- SRTM 30×30m database for catchment areas
- Drone surveys for dam and powerhouse areas
- Pleiades satellite imagery (50cm accuracy)
- 22 Ground Control Points established
Hydrology
Key hydrological findings:
- Multi-annual average discharge at Dabus near Assosa: ~146 m³/s
- Design flood (10,000 year return period): 2,160 m³/s
- Sediment yield: 500 t/km²/year
Geology and Geotechnics
Main geological characteristics:
- Dam sites founded on Precambrian meta-granite and meta-granodiorite
- Rock quality generally "strong" to "very strong"
- Quarry sites identified for construction materials
Seismic Assessment
Return Period (years) | Peak Ground Acceleration (PGA/g) |
---|---|
475 | 0.05 |
950 | 0.07 |
2,500 | 0.10 |
10,000 | 0.15 |
Economic Analysis
The project shows strong economic viability:
Plant | IRR | Payback Period |
---|---|---|
Dabus ch-130 | ~18% | 4 years |
Dabus ch-108 | 30-33% | 2 years |
Client Comments and Consultant Responses
The document includes extensive comments from the client (Ministry of Water, Irrigation and Energy) and detailed responses from the consultant (Studio Ing. G. Pietrangeli). Key areas addressed include:
- Hydrological modeling approaches
- Dam safety considerations
- Environmental impact assessment requirements
- Transmission system design
- Social and economic impacts
The consultant has committed to address all comments in Revision B of the Pre-Feasibility Report.
Next Steps
The project will proceed to the Feasibility Study phase, which will address:
- More detailed site investigations
- Refined engineering designs
- Comprehensive Environmental and Social Impact Assessment
- Final transmission system design