Boyo Regulating Dam Project Contract Summary
Project Overview
Project: Boyo Regulating Dam Project
Parties: Water Resources Development Authority (Employer) and Ethiopian Water Works Construction Authority (Contractor)
Contract Date: January 1986
Contract Price: 4,213,678.90 Birr
Contract Documents
- Drawings
- Specifications
- Bill of Quantities
- Contract Agreement
- General Conditions
Major Work Sections
Section | Description | Amount (Birr) |
---|---|---|
A | Access Road | 304,000.00 |
C | Cofferdams and Unwatering | 53,886.00 |
E | Rock Excavation | 472,600.00 |
F | Concrete | 374,850.00 |
L | Embankment | 1,431,600.00 |
M | Stone Masonry | 96,440.00 |
Key Specifications
Construction Requirements
- All materials and workmanship must be new and of suitable grade
- Contractor responsible for site conditions and local regulations
- Engineer has authority to interpret drawings and specifications
Payment Terms
- 30% advance payment within 21 days of contract signing
- Monthly progress payments with 10% retention
- Final payment upon completion and acceptance
Insurance Requirements
- Works insurance covering all construction activities
- Third-party liability insurance
- Workmen's compensation insurance
Contract Conditions
Changes to Contract
Engineer may order changes within general scope of contract. Contractor must submit change proposals with detailed cost breakdowns.
Delays and Forfeiture
Contractor may forfeit rights for failure to complete on time, except for delays beyond Contractor's control (force majeure events).
Special Risks
Contractor not liable for damages from war, civil unrest, or other special risks. Employer must indemnify Contractor for such events.