Birete Dam Project Specifications and Bill of Quantities
Project Overview
The Birete Dam Project document contains detailed specifications for construction and a comprehensive bill of quantities. Prepared by the Ministry of Mines, Energy and Water Resources (Land and Water Studies Agency) in Addis Ababa, May 1981.
Key Features:
- Environmental protection measures including landscape preservation and water pollution prevention
- Two-stage river diversion scheme during construction
- Earth and rockfill dam construction with multiple material zones
- Concrete structures including spillway, diversion structure, and intake structure
- Miscellaneous works including drainage systems, gates, and steel pipes
Main Project Sections
Section A: Environmental Protection
- Landscape preservation requirements
- Water pollution prevention measures
- Dust abatement procedures
Section B: Mobilization for Project Construction
- Contractor's responsibilities for facilities and services
- Payment structure for mobilization work
Section C: Diversion and Care of Water During Construction
- Two-stage diversion scheme description
- Cofferdam construction specifications
- Water management procedures
Section D: Excavation
- Classification of excavation materials (Rock, Random Rock, Formation, Earth)
- Excavation methods and tolerances
- Foundation preparation requirements
Section E: Construction of Earth and Rockfill
- Material specifications for different dam zones
- Placement and compaction procedures
- Moisture control requirements
Section F: Concrete, Plain and Reinforced
- Concrete composition and quality requirements
- Formwork, placing, and curing specifications
- Reinforcement steel standards
Section G: Miscellaneous
- Structural drainage systems
- Bulkhead gates and trash rack installation
- Steel pipes and valves for intake structure
Key Material Specifications
Dam Construction Materials
Material Zone | Description | Key Requirements |
---|---|---|
Riprap | Upstream slope protection | Angular, sound, durable rock blocks (70-8cm size range) |
Rockfill Shells | Upstream/downstream shells | Angular, sound rock (max 30cm size) |
Transition Material | Adjacent to impervious core | Weathered basalt (max 8cm size) |
Impervious Core | Clay core | Natural clay deposits from designated borrow area |
Concrete Requirements
Component | Specification |
---|---|
Cement | Portland Cement conforming to BS 12:1958 or ASTM C 150-64 |
Aggregates | Graded natural or manufactured sand and gravel/crushed rock |
Water-Cement Ratio | 0.45 to 0.6 depending on structure requirements |
Curing Period | Minimum 14 consecutive days |
Bill of Quantities Highlights
Major Quantities
Item | Quantity | Unit |
---|---|---|
Rockfill Zone | 123,500 | m³ |
Impervious Fill (Clay core) | 48,000 | m³ |
Impervious Fill (Clay blanket) | 128,000 | m³ |
Reinforced Concrete | 1,600 | m³ |
Reinforcing Steel | 126,630 | kg |
Portland Cement | 130 | tons |
Key Structures
- Diversion Structure with bulkhead gate
- Intake Structure with trash rack and bulkhead gate
- Spillway structure
- 49.2m of 50cm diameter steel pipe for intake
- Butterfly valves (50cm and 30cm)
Construction Methodology
Diversion Scheme
The construction will follow a two-stage diversion approach:
- Stage I (First Dry Season):
- Construct diversion structure, spillway, and intake structure
- Build dam embankment from both sides leaving a central gap
- Stage II (Next Dry Season):
- Construct upstream and downstream cofferdams
- Divert river through diversion structure
- Close gap in main dam and complete construction
Dam Construction
- Compaction requirements:
- Impervious core: ≥10 passes with tamping roller
- Other zones: ≥4 passes with vibratory roller
- Layer thicknesses:
- Impervious material: ≤15cm compacted
- Transition material: ≤25cm compacted
- Rockfill: ≤30cm compacted
Quality Control & Measurement
Testing Requirements
- Regular testing of materials and embankment construction
- Concrete strength tests at 7 and 28 days
- Aggregate grading and quality checks
- Moisture content control for impervious fill
Measurement Methods
- Earthworks: Actual measurement of materials in place
- Concrete: Volume within neat lines of structures
- Pumping: Measurement of water removed (5 liters/sec/hour)
- Reinforcement: Based on lengths installed converted to weights
Payment Structure
- Lump sum payments for mobilization and river diversion
- Unit rate payments for most construction items
- Separate payments for cement, reinforcement, and embedded items