Birete Dam Project - Specifications and Bill of Quantities
Project Overview
Ministry: Ministry of Mines, Energy and Water Resources, Land and Water Studies Agency
Location: Addis Ababa, Ethiopia
Date: May 1981
Purpose: This document contains specifications for the construction of Birete Dam Project, including payment clauses tied to the Bill of Quantities.
Key Specifications Sections
Section A: Environmental Protection
- Landscape preservation requirements
- Prevention of water pollution measures
- Dust abatement procedures
Section B: Mobilization for Project Construction
- Contractor responsibilities for facilities and services
- Payment structure as a lump sum for mobilization
Section C: Diversion and Care of Water During Construction
- Two-stage diversion scheme (dry season construction)
- Cofferdam construction requirements
- Measurement and payment details for various water management activities
Section D: Excavation
- Classification of excavation materials (Rock, Random Rock, Formation, Earth)
- Excavation methods and tolerances
- Quarry operations for rock and transition materials
- Foundation preparation requirements
Section E: Construction of Earth and Rock Fill
- Material specifications for:
- Riprap slope protection
- Rock-fill shells
- Transition material
- Impervious core (clay)
- Placement, spreading, and compaction requirements
- Moisture control procedures
Section F: Concrete, Plain and Reinforced
- Composition and quality requirements
- Cement specifications and storage
- Aggregate gradation requirements
- Concrete mixing, placing, and curing procedures
- Formwork and finishing standards
- Reinforcement steel specifications
Section G: Miscellaneous
- Structural drains installation
- Bulkhead gates and trash rack specifications
- Welding and fabrication standards
Key Bill of Quantities Items
Item No. | Description |
---|---|
101 | Mobilization for Project Construction |
102 | River Diversion and Care of Water |
103-a to 104-a, 201 | Clearing and Stripping of Foundations |
103-b, 202 | Earth Excavation in foundations |
203 | Random-Rock Excavation in foundations |
204 | Rock Excavation in foundations |
301-306 | Main Dam Fills (Riprap, Rockfill, Transition Material, Impervious Fill, etc.) |
401 | Furnish Portland Cement |
402 | Furnish and Install Reinforcing Steel |
403 | Furnish and Install Water Stop |
404-407 | Various Concrete Works (Dental, Blinding, Plain, Reinforced) |
Key Technical Specifications
Material Gradations
Material | Gradation Requirements |
---|---|
Riprap | 70cm (100%), 60cm (80-90%), 15cm (10-20%), 8cm (≤10%) |
Rock-fill | 30cm (100%), No.4 sieve (≤25%), No.200 sieve (≤5%) |
Transition Material | 8cm (100%), 2cm (50-80%), No.4 sieve (25-50%), No.200 sieve (5-15%) |
Concrete Specifications
- Cement content: 200-365kg/m³ depending on structural requirements
- Water-cement ratio: 0.45 to 0.6
- Maximum slump: 3 inches (8cm)
- Curing period: Minimum 14 consecutive days
Compaction Requirements
- Impervious core: Minimum 10 passes with tamping roller
- Other zones: Minimum 4 passes with vibratory roller
- Layer thicknesses:
- Impervious: ≤15cm compacted
- Transition: ≤25cm compacted
- Rockfill: ≤30cm compacted