Birete Dam Project Hydrological Study Summary
Project: Birete Dam Hydrological Study
Location: Shoa administrative region, Ethiopia (106 km NW of Addis Ababa)
Coordinates: 9°29'N, 38°20'E
Authors: NAPIS AHMAD, GIRMA BEKELE, BANTEYEHUN HALLE
Date: April 1980
1. Introduction
The Birete Dam Project was planned to conserve surface runoff to meet water requirements for a proposed cement factory. The dam site was selected on Birete River, a tributary of Sodoble River which drains into Muger River.
2. Key Findings
Water Requirements
- Present demand: 2,000 m³/day (23.15 litres/sec) for cement factory
- Future increased demand anticipated
Water Availability
Parameter | Value |
---|---|
Catchment Area | 37.85 km² |
Annual Rainfall (Derba station) | 890.8 mm to 1,143.8 mm (1975-1978) |
Annual Evaporation (Hine station) | 1,499.1 mm to 1,624.2 mm (1976-1978) |
Base Flow (minimum recorded) | 11 litres/sec |
Dam Specifications
Option | Height (m) | Total Storage (m³) | Live Storage (m³) | Dead Storage (m³) | Draught (litres/sec) |
---|---|---|---|---|---|
Recommended | 20.5 | 3.0 × 10⁶ | 2.0 × 10⁶ | 1.0 × 10⁶ | 94 |
Alternative 1 | 19.7 | 2.5 × 10⁶ | 1.5 × 10⁶ | 1.0 × 10⁶ | 68 |
Minimum | 17.5 | 1.5 × 10⁶ | 0.5 × 10⁶ | 1.0 × 10⁶ | 23.15 |
Design Flood
Multiple methods were used to estimate peak flood discharge:
- Fiddes method: 111.2 m³/sec
- Modified Myers's method: 104.6 m³/sec
- Blue Nile Basin report (100-year flood): 83 m³/sec
- Shim's formula: 96.9 m³/sec
- Triangular hydrograph concept: 137.2 m³/sec
- Unit hydrograph method: 209.45 m³/sec (adopted for design)
Spillway Design
- Crest length: 31 meters (semicircular shape)
- Maximum discharge: 122.5 m³/sec
- Maximum reservoir level during flood: 126.58 m
- Crest level: 125.00 m
- Head above crest: 1.58 m
- Surcharge volume: 954,000 m³
Sedimentation
- Assumed annual sediment inflow: 1 mm depth over catchment
- Estimated sediment volume: 37,850 m³/year
- Dead storage life: 26 years
- Trap efficiency: 80%
3. Conclusions
- The study recommends a 20.5m high dam with 3.0 million m³ total storage (2.0 million m³ live storage)
- Design flood peak of 209.45 m³/sec was adopted for spillway design
- A 31m semicircular spillway crest was designed to limit head to 1.5m
- The study acknowledges limitations due to scarce data and recommends caution in applying methods to other basins
- Mass curve analysis shows sufficient water availability for the cement factory's needs