Birete Dam Project Hydrological Study Summary
Project Overview
The Birete Dam Project was a hydrological study conducted in April 1980 to assess water availability for a proposed cement factory in Ethiopia. The study was prepared by Nafis Ahmad (UN Engineering Adviser), Girma Bekele, and Banteyehun Halle of the Land and Water Studies Agency.
Key Project Details:
- Location: Birete River basin, 106 km NW of Addis Ababa (9°29'N, 38°20'E)
- Catchment Area: 37.85 km²
- Purpose: Water supply for cement factory (current demand: 23.15 l/s)
- Dam Type: Fill-dam
Methodology
The study used limited available data from nearby stations (Derba for rainfall, Hino for evaporation) and applied various hydrological methods including:
- U.S. Soil Conservation Service method for runoff estimation
- Mass curve analysis for water availability
- Multiple empirical methods for flood peak estimation
- Unit hydrograph approach for design flood derivation
- Flood routing to determine spillway capacity
Key Findings
Water Availability
Scenario | Live Storage (million m³) | Dead Storage (million m³) | Draught (l/s) | Reservoir Elevation (m) |
---|---|---|---|---|
Recommended | 2.0 | 1.0 | 94 | 125 |
Alternative 1 | 1.5 | 1.0 | 68 | 124.2 |
Minimum | 0.5 | 1.0 | 23.15 | 122 |
Design Flood
Multiple methods were used to estimate the 100-year flood peak:
- Fiddes method: 111.2 m³/s
- Modified Myers's method: 104.6 m³/s
- Blue Nile Basin curve: 83 m³/s
- Triangular hydrograph concept: 137.2 m³/s
- Unit hydrograph approach: 209.45 m³/s (adopted for design)
Dam Specifications
Parameter | Value |
---|---|
Recommended Height | 20.5 m (including 3 m freeboard) |
Total Storage Capacity | 3.0 million m³ |
Spillway Capacity | 122.5 m³/s (31m crest length) |
Maximum Reservoir Level | 126.58 m |
Sediment Life | 26 years (based on 1 mm/year erosion assumption) |
Conclusions
The study recommends:
- A 20.5 m high dam with 3.0 million m³ total storage (2.0 million m³ live storage)
- A semicircular spillway with 31m crest length capable of handling 209.45 m³/s design flood
- Provision for future water demand increases (current factory demand is only 23.15 l/s)
- 1.0 million m³ dead storage for sediment accumulation over 26 years
Note: The authors caution that the study is based on very limited data and results should not be generalized to other basins.
Appendices
The report includes two appendices:
- Appendix A: Mr. C.A. Munoz's note with additional hydrometeorological data and flood peak calculations
- Appendix B: Area and volume computations for reservoir capacity curves