×

Summery

Bilate River Basin Development Study Summary

Bilate River Basin Development Study - Summary

1. Introduction

The Bilate River Basin Study was initiated to address water shortages for irrigation in the Lower Bilate Valley, particularly for the Bilate Agricultural Estate (BAE). The study identified potential dam sites for water storage and hydropower generation along the Bilate River.

Key Objective: Identify dam and reservoir sites to control and store sufficient water for irrigation in the Lower Bilate sub-basin while considering other water uses.

2. Basin Description

The Bilate River Basin covers 7,463 sq.km in Ethiopias Shoa and Sidamo provinces, with elevations ranging from 1,285m to 3,600m. The basin is divided into three sub-basins:

Sub-Basin Area Characteristics
Upper Bilate Upstream of Boyo Swamp Steep gradients, unsuitable for large reservoirs
Mid Bilate Boyo Swamp to Blatentena 4,500 ha potentially irrigable land
Lower Bilate Blatentena to Lake Abaya 7,780-10,000 ha irrigable land

3. Hydrometeorology

Key findings about water resources:

  • Annual rainfall: 600mm (lowlands) to 1,200mm (highlands)
  • Average annual flow at Alaba Colito: 11.2 m³/s (351.2×10⁶ m³/year)
  • Minimum recorded flow: 135 l/s (April 1973)
  • Water quality issues during low flow periods (high mineral concentration)

4. Proposed Technical Solutions

4.1 Boyo Swamp Dam

  • Location: 800m downstream of Boyo Swamp outlet
  • Type: Concrete diversion weir with radial gates
  • Storage capacity: 184×10⁶ m³ (160×10⁶ m³ net after siltation)
  • Primary purpose: Irrigation water supply

4.2 Hydropower Plants

Plant Capacity Annual Production Estimated Cost
Boyo Swamp 5,800 kW 18.9×10⁶ kWh 4.2 million Eth. $
Alaba Colito 5,000 kW 16.2×10⁶ kWh 5.0 million Eth. $
Ropi Water Falls 11,000 kW 36.0×10⁶ kWh 6.0 million Eth. $

5. Economic Analysis

Comparative costs of water storage and energy production:

Project Water Storage Cost (Eth. $/m³) Energy Cost (Eth. $/kWh)
Boyo Swamp 0.0116 (capital)
0.072 (annual)
0.020
Ropi Dam 0.116 (capital)
0.78 (annual)
0.026

Key Finding: Boyo Swamp storage is 10 times cheaper than Ropi Dam for water storage. Ropi Water Falls hydropower is the most economical for electricity generation.

6. Conclusions and Recommendations

  1. Boyo Swamp Dam is the most feasible solution for irrigation water needs (technically and economically)
  2. Ropi Water Falls Hydro Power Plant should be implemented first for electricity generation
  3. Detailed studies should continue for Boyo Swamp dam and Ropi Water Falls power plant
  4. Construction of Boyo Swamp dam could begin in 1975 for completion by 1976 rainy season
  5. The development would support irrigation for 10,000 ha and provide electricity to regional towns