Beshilo Hydroelectric Reconnaissance Study Report Summary
Prepared by: Water Resources Development Authority, Ethiopia
Date: August 1995
1. Project Overview
The Beshilo Hydroelectric Project is part of Ethiopia's Medium Scale Hydropower Development (MSHD) program, focusing on sites with capacities of 40-60 MW. Three potential sites were investigated along the Beshilo River, a tributary of the Blue Nile:
Site | Location (Coordinates) | Drainage Area (km²) | Mean Annual Flow (m³/s) |
---|---|---|---|
Abbay-20 | 11°24'23"N, 39°02'15"E | 3,548 | 22.75 |
Abbay-21 | 11°22'37"N, 38°53'37"E | 4,728 | 30.56 |
Abbay-22 | 11°25'35"N, 38°42'36"E | 5,136 | 33.16 |
The study was conducted to address Ethiopia's acute power shortage, with only about 370 MW (less than 1%) of the estimated 15,000-30,000 MW hydropower potential being exploited by 1995.
2. Key Findings by Site
Abbay-20
- Dam Type: Concrete-faced rockfill
- Height: 92m
- Installed Capacity: 29.5 MW (2 Francis turbines)
- Annual Energy: 86.3 GWh
- Reservoir: 550.64 MCM at max level
- Key Challenge: Fault lines near dam site (Fault-A and Fault-B)
- Construction Materials: Basalt quarry available 6km upstream
Abbay-21
- Dam Type: Concrete gravity
- Height: 92m
- Installed Capacity: 38.9 MW (2 Francis turbines)
- Annual Energy: 118 GWh
- Reservoir: 1,057.97 MCM at max level
- Key Challenge: Fault 500m downstream of dam
- Construction Materials: No nearby quarry site
Abbay-22
- Dam Type: Concrete gravity
- Height: 92m
- Installed Capacity: 44.56 MW (3 Francis turbines)
- Annual Energy: 130 GWh
- Reservoir: 600.87 MCM at max level
- Key Challenge: Thin basalt layers within thick tuff/ash
- Construction Materials: Would require hauling from 36km away
3. Comparative Evaluation
Criteria | Abbay-20 | Abbay-21 | Abbay-22 |
---|---|---|---|
Project Cost (million USD) | 171.1 | 273.9 | 229.3 |
Unit Energy Cost (US cents/kWh) | 30.5 | 31.4 | 17.67 |
Access Road Length (km) | 118 | 123 | 170 |
Land Inundated (ha) | 850 | 1,623 | 1,033 |
Environmental Impact | Moderate | Moderate | Moderate |
Overall Recommendation: Abbay-20 is considered the most feasible option for immediate implementation due to better accessibility and available construction materials, despite geological challenges with fault lines.
4. Key Challenges
- Geological: Highly weathered basalt, tuff and ash formations; fault lines at Abbay-20; potential reservoir leakage
- Hydrological: Ungauged river with high sediment load expected (10-25% of storage as dead storage provision)
- Access: Extremely difficult terrain requiring helicopter access during survey
- Environmental: Loss of agricultural land along river banks, potential malaria increase
- Social: Displacement of farmers using river banks for seasonal cultivation
5. Recommendations
Immediate Next Steps:
- Conduct detailed topographic surveys with 1:50,000 scale mapping
- Perform comprehensive geological investigations including:
- Slope stability analysis
- Reservoir sedimentation studies
- Permeability tests for water tightness
- Fault zone investigations
- Establish hydrological monitoring stations on Beshilo River
- Conduct detailed Environmental Impact Assessment
- Improve access roads for further studies
Long-Term Development Strategy:
Consider cascaded development of Abbay-20 followed by Abbay-22 to optimize infrastructure use, pending results of further studies.
6. Project Benefits
- Address Ethiopia's acute power shortage (forecasted to begin in 1995)
- Provide renewable energy to support regional development
- Potential flood protection benefits downstream
- Employment opportunities during construction and operation
- Infrastructure development (roads, possibly schools and clinics) in remote area
The project aligns with Ethiopia's national priority to develop its hydropower potential to support economic growth and reduce reliance on biomass fuels (90% of energy consumption) and imported diesel (10% of electric generation).