Beko-Abo Multipurpose Project - Reconnaissance Study Summary
Project Overview
The Beko-Abo Multipurpose Project is a proposed hydropower and water resource development on the Abay River (Blue Nile) in Ethiopia. This reconnaissance study evaluates the project as an alternative to the previously planned Karadobi Multipurpose Project.
Key Findings
- Location: About 2 km upstream of the Nkemte-Bahar Dar Road Bridge crossing the Abay River
- Purpose: Avoid conflict with the new Kessie Bridge (under construction) that would have been submerged by the Karadobi project
- Dam Height: Approximately 270m high Roller Compacted Concrete (RCC) gravity dam
- Reservoir: Full Supply Level at 1065 masl with active storage of 20,000 million m³
- Power Generation: Estimated 2,100 MW installed capacity producing 11,200 GWh/year
- Cost Estimate: Approximately $2.84 billion USD
Comparison with Karadobi Project
Parameter | Karadobi | Beko-Abo | Difference |
---|---|---|---|
Dam Height | 250m | 270m | +20m |
Installed Capacity | 1,600 MW | 2,100 MW | +31% |
Annual Energy Generation | 8,634 GWh | 11,200 GWh | +30% |
Reservoir Surface Area | 445 km² | 420 km² | -6% |
Active Storage Volume | 17,000 million m³ | 20,000 million m³ | +18% |
Dam Volume | 6.5 million m³ | 10.5 million m³ | +62% |
Project Benefits
- Higher energy production potential (28-30% more than Karadobi)
- Better access to site via existing road infrastructure
- Avoids submergence of the new Kessie Bridge
- Provides downstream benefits including flood control and sediment trapping
- Improves regulation for existing hydropower projects in Sudan
Environmental Considerations
The study notes that while detailed environmental surveys were not conducted, some key observations include:
- Reservoir area of 420 km² (smaller than Karadobi's 445 km²)
- Low population density in affected area with mostly seasonal cropping
- Potential impacts on fish migration but no critical biodiversity concerns identified
- Significant downstream benefits for Sudan including reduced sedimentation and improved dry season flows
Conclusion
The Beko-Abo Multipurpose Project appears technically feasible and offers several advantages over the Karadobi project, particularly in terms of energy production potential and infrastructure compatibility. The cost per kWh is comparable (0.253 USD/kWh for Beko-Abo vs 0.258 USD/kWh for Karadobi). Further detailed studies would be needed to confirm the preliminary findings of this reconnaissance report.