Baro Hydropower Projects Pre-Feasibility Study
Project: Baro 1 and Baro 2 Hydropower Projects in Ethiopia
Prepared by: Norplan A.S in association with Norconsult International A.S.
Date: 16.04.1999
Document: Executive Summary - Volume 1
1. Project Overview
The Baro 1 and Baro 2 Hydropower Projects are located in the upper part of the Baro-Akobo basin in western Ethiopia, between Gore and Bonga. These cascaded schemes exploit a 30 km stretch of the upper Baro River with a total gross head of 690 meters.
2. Key Project Characteristics
Parameter | Baro 1 | Baro 2 |
---|---|---|
Installed Capacity (MW) | 170 | 483 |
Dependable Capacity (MW) | 151.8 | 482.5 |
Firm Energy (GWh/y) | 647 | 2,094 |
Gross Head (m) | 185 | 505 |
Plant Factor | 0.4 | 0.4 |
Total Construction Cost (USD million) | 130 | 568 |
3. Economic Analysis
Alternative | ERR % | NPV (USD million)* | B/C Ratio |
---|---|---|---|
Baro 1 + Baro 2 + reservoir dam | 13 | 198.1 | 1.4 |
Baro 2 + reservoir dam | 12 | 110.7 | 1.3 |
Baro 1 - reservoir dam | 16 | 72.8 | 1.6 |
* At 10% discount rate
4. Technical Features
Baro 1 Project
- Concrete faced rockfill dam (CFRD) with height of 81m
- Reservoir with total storage of 800 million m³
- Underground powerhouse with 2 Francis turbine units
- 4.5 km waterway conduit
Baro 2 Project
- RCC dam with height of 30m
- Small regulating pond (20 million m³)
- Underground powerhouse with 5 Francis turbine units
- 11.4 km waterway conduit
5. Hydrology
The projects utilize 30-year flow series based on records from the Metin gauging station:
- Baro 1: Catchment area 2,210 km², mean annual flow 73.8 m³/s
- Baro 2: Catchment area 2,332 km², mean annual flow 77.5 m³/s
About 87% of annual flows occur during July-October period.
6. Transmission
The projects require connection to the grid via 420 kV transmission lines:
- Baro 1 to Ghedo/Gilgel Gibe: 326/320 km
- Baro 2 to Ghedo/Gilgel Gibe: 349/343 km
7. Recommendation
The study recommends constructing Baro 2 and the reservoir dam first, followed immediately by Baro 1 due to its high Economic Rate of Return (16%). Both projects should be considered in further studies.