Feasibility Study of Baro 1 and 2 Hydropower Projects
Desk Study on Genji Diversion Alternative C II
Document Overview
This report presents a desk study comparing the Genji Diversion Alternative C II with the original Baro 1-2 hydropower scheme in Ethiopia. The study evaluates geological, hydrological, environmental, and cost factors.
Key Recommendations
- The Feasibility Study should focus on the original Baro 1-2 scheme including Genji Diversion Alternative A
- Genji Diversion Alt. C II is not recommended for further study at this time
- Increasing the Baro 1 reservoir volume may be preferable to Genji diversion options
Comparison of Options
Option | Key Features | Energy Production | Environmental Impact |
---|---|---|---|
Baro 1-2 (Original) | Two dams on Baro River | 3100 GWh average annual | 4050 ha forest inundation |
Genji C II Option 1 | 120m RCC dam on Genji River | Marginally higher than Baro 1-2 | Slightly higher impact than Baro 1-2 |
Genji C II Option 2 | Maintains both Genji and Baro 1 reservoirs | Significant dry season energy increase | Very unfavorable (1130 million m³ reservoir) |
Genji C II Option 3 | Genji dam raised 10m | Less favorable than Option 2 | 40 km² inundation |
Increased Baro 1 Reservoir | Baro 1 dam raised 15m | Similar to Genji Option 2 | 36 km² inundation |
Key Findings
Cost Analysis
- Specific construction costs are similar across all options (~0.19 USD/kWh)
- Genji options generally have higher construction costs than Baro 1-2
- RCC dam costs decrease with increasing volume (62-95 USD/m³)
Geological Conditions
- Genji tunnels may require more rock support than Baro tunnels
- Some areas may need lining for leakage prevention
Hydrological Conditions
- Annual rainfall ranges from 1700mm at dam sites to 2300mm in higher elevations
- Runoff in upper Baro region slightly higher than Sor river (key comparison site)
- Flood analysis shows peak discharges up to 2250 m³/s for PMF at Baro sites
Environmental Assessment
- Baro 1 (1520m level) would flood ~4050 ha of mostly forest land
- Genji (1350m level) would flood ~3840 ha with more agricultural impact
- Genji reservoir would be longer (31km vs 17km) affecting more communities
Conclusion
The study concludes that Genji Diversion Alternative C II does not offer sufficient advantages over the original Baro 1-2 scheme to justify further investigation. While some options could increase energy production, they would do so at higher environmental costs. The recommendation is to focus on the Baro 1-2 scheme with possible consideration of increasing the Baro 1 reservoir volume.