Summary of Baro Multipurpose Project Feasibility Study - Geology and Geotechnics
Project Overview
The Baro Multipurpose Project consists of three hydropower schemes in Ethiopia:
- Baro 1: Upstream plant with 200m gross head, 3.5km waterways
- Baro 2: Downstream plant with 510m gross head, 12.7km waterways
- Genji Diversion: Tributary scheme with 390m gross head, 5.9km waterways
Geological Setting
The project areas are underlain by Precambrian crystalline basement rocks (Alghe Group) overlain by Tertiary basalt lava flows (Mekonen Basalts). Significant areas are blanketed by red lateritic soil with scattered alluvial deposits along riverbanks.
Regional Geology
The Western Ethiopia Shield where the project is located consists of:
- Gneisses and migmatites at upper amphibolite metamorphic grade
- Basaltic lava flows uncomfortably overlying the Precambrian basement
- Vesicular basalt with large plagioclase phenocrysts found at about 1300 masl
Site Investigations
Comprehensive investigations were conducted including:
Core Drilling Program
Project Area | Number of Boreholes | Total Length Drilled (m) |
---|---|---|
Baro 1 Dam Site | 7 | 381.8 |
Baro 1 Tunnels | 6 | 558.2 |
Baro 2 Dam Site | 4 | 151.9 |
Baro 2 Tunnels | 6 | 772.7 |
Genji Dam Site | 2 | 81.2 |
Genji Tunnel | 1 | 100.4 |
Total | 26 | 2046.2 |
Key Findings from Investigations
Soil Conditions
- Baro 1: Soil thickness varies from 4m to 51m (residual soil from gneiss/basalt)
- Baro 2: Right bank has thin soil (0-6m), left bank has thicker cover (13-16m)
- Genji: Modest soil cover (0-6m) with rock exposed in riverbed
Rock Quality (RQD)
Rock Quality Designation classification:
- Baro 1 Dam: Highly variable - from 0% High/Very High in B1D-4 to 77-83% in B1D-1/-7
- Baro 1 Tunnels: Generally good - 80-98% High/Very High in most boreholes
- Baro 2/Genji: Generally high quality - >90% High/Very High in most dam site boreholes
Rock Strength (UCS)
Project Area | Low Strength (%) | Medium Strength (%) | High Strength (%) | Very High Strength (%) |
---|---|---|---|---|
Baro 1 | 0 | 56 | 44 | 0 |
Baro 2/Genji | 8 | 34 | 58 | 0 |
Permeability
Generally low to very low permeability, with higher values in jointed zones at dam abutments requiring grouting.
Groundwater
Water table depths vary significantly (5-28m at Baro 1, 8-23m at Baro 2) with seasonal variations expected.
Engineering Recommendations
Dam Foundations
Baro 1: Combination dam recommended:
- Concrete spillway in narrow gorge on competent bedrock
- Main CFRD across main valley (partly founded on firm residual soil)
- Saddle dams as clay core embankments
Baro 2:
- Concrete spillway and intake at right riverbank
- Clay core rockfill dams on both sides
- Special measures needed for high permeability layer on left bank
Genji: Massive concrete dam recommended due to favorable foundation conditions.
Tunneling Conditions
Precambrian basement rocks are suitable for tunnel construction with sufficient quality for self-supporting openings. Recommended support measures include:
- Rock bolting with steel fiber reinforced sprayed concrete in general
- Heavier structural support (reinforced sprayed concrete arches or cast lining) in weakness zones
- Cement grouting for leakage zones
Construction Materials
- Gneiss rock suitable for concrete aggregates and rockfill
- Natural sand/gravel scarce - crushed rock recommended for concrete and filters
- No Alkali-Silica Reactivity detected with local cement
Conclusions
The geological and geotechnical investigations demonstrate the technical feasibility of the Baro Multipurpose Project. The Pre-cambrian basement rocks provide suitable conditions for dam foundations and tunneling, though with some variability in rock quality requiring appropriate engineering solutions.
Key Recommendations:
- Seismic refraction profiling should be conducted during detailed design phase
- Additional test pits needed on left banks (couldn't be excavated due to weather)
- Rock stress measurements required for detailed powerhouse cavern design