Master Drainage Plan for Melka Sadi and Amibara Areas - Final Report (July 1985)
1. Introduction
This engineering annex (Volume 7, Annex D) presents the Master Drainage Plan for the Melka Sadi and Amibara areas in Ethiopia. The study was conducted by the Water Resources Development Authority of Ethiopia in collaboration with consulting engineers Sir William Halcrow & Partners.
Key Background Information:
- The study area comprises the right bank flood plains of the Middle Awash River
- Existing problems include rising groundwater tables and inadequate drainage systems
- The plan addresses both surface and subsurface drainage requirements
- Implementation is proposed in stages, with Stage I covering 6,200 ha gross area
2. Current Irrigation Systems and Deficiencies
2.1 Existing Irrigation Practices
The area has both gravity-fed and pumped irrigation systems serving various state farms and research stations. Key observations include:
- Water distribution is regulated through various structures including check drops, primary offtakes, and spillways
- Furrow irrigation is the predominant method with typical furrow lengths of 200-250m
- Measurement facilities are inadequate in many areas
2.2 Major Deficiencies
Deficiency | Impact | Recommended Improvement |
---|---|---|
Poor land leveling | Uneven water distribution, fields out of command | Land planing and leveling |
Lack of control structures | Inefficient water distribution | Installation of gated offtake structures |
Inadequate water measurement | Poor water management | Installation of measurement devices |
Seepage losses (0.20 l/sec/1000m²) | Water wastage, rising water tables | Potential canal lining |
3. Drainage Planning and Master Plan
3.1 Drainage Requirements
The study identified critical drainage needs:
- Existing surface drainage is inadequate with ill-defined natural drainage lines
- Subsurface drainage is virtually non-existent except for a small pilot area
- Groundwater tables are rising at about 1m/year in affected areas
- Projections indicate water tables will rise to within 1m of surface over 2,200ha in Melka Sadi and 1,600ha in Amibara by 1988
3.2 Master Drainage Plan Components
- Buried field lateral drains at 1.8m depth with spacings from 30-110m
- Buried collector drains conveying water to deep open drains
- In-field and tertiary surface drains
- Deepening and widening of existing secondary and main drains
- New drainage outfall into the Awash River
- Flood protection works including dyke realignment
Implementation Strategy:
The plan proposes a 15-year implementation period (1985-2000) with Stage I covering 6,200 ha (gross) requiring 4-5 years. The implementation schedule is designed to address the most critical areas first, particularly in Melka Sadi where conditions are deteriorating rapidly.
4. Key Design Elements
4.1 Drainage Network Design
The design includes:
- Surface Drainage: Field drains, tertiary drains (400 l/sec capacity), and deep open secondary/main drains
- Subsurface Drainage: 60mm corrugated PVC pipes for laterals with red ash envelopes; 150-300mm pipes for collectors
- Structures: Culverts, bridges, outfalls, and manholes
4.2 Design Criteria
Parameter | Value |
---|---|
Subsurface drainage rate (bananas) | 3.4 mm/day |
Subsurface drainage rate (cotton) | 2.5 mm/day |
Tertiary drain capacity | 400 l/sec |
Minimum drain velocity | 0.3 m/s (preferably 0.4 m/s for bilharzia control) |
4.3 Flood Protection
The plan includes:
- Western (Awash) flood dyke - 55km length requiring heightening in some sections
- Eastern catchment dyke extension - 32km length designed for 1:10 year flood
- Realignment of 4.2km of dyke at critical locations
5. Implementation and Costs
5.1 Construction Methods
The plan recommends:
- Specialized trenching machines for pipe installation (estimated output: 52km/month/machine)
- On-site production of PVC pipes (estimated cost: 2.72 Birr/m for 60mm pipe)
- Contract-based implementation rather than direct labor
5.2 Cost Estimates
Component | Cost (Birr) |
---|---|
Stage I Development (1985-90) | 28,407,000 |
Full Masterplan (1985-2000) | 90,859,000 |
Unit cost (Stage I) | 7,252/ha (US$ 3,502/ha) |
5.3 Operation and Maintenance
Key requirements include:
- Specialized drain jetting equipment for subsurface maintenance
- Additional hydraulic excavators for open drain maintenance
- Strengthening of the Project Control Centre organization
- Estimated annual recurrent costs: 2.5% of capital cost for surface drains, 0.5% for pipes
6. Conclusions and Recommendations
Key Recommendations:
- Immediate implementation of Stage I works in the most affected areas
- Improvements to irrigation water management practices
- Strengthening of organizational structures for water management
- Contract-based implementation using specialized equipment
- Comprehensive monitoring and maintenance program
The Master Drainage Plan presents a comprehensive solution to the drainage problems in the Melka Sadi and Amibara areas, addressing both immediate needs and long-term requirements through a phased implementation approach.