Amibara Project Design Report Summary
Prepared by: Sir William Halcrow & Partners
Date: September 1973
Client: Imperial Ethiopian Government - Awash Valley Authority
1. Project Overview
The Amibara Irrigation Project is a major development in Ethiopia's Awash Valley, designed to irrigate approximately 10,000 hectares of land for cotton cultivation and other crops. The project represents a central component of the broader Awash Valley development scheme.
Key Components:
- River diversion structure at Melka Sadi
- Main and primary supply canals
- Primary and secondary drainage systems
- Flood protection dykes (western and eastern)
- Road network and bridges
- Settlement villages and housing
- Administrative centers
2. Key Design Decisions
2.1 Single Diversion Structure
The report recommends using a single barrage at Melka Sadi rather than two structures (as previously proposed by Italconsult), citing:
- Estimated cost savings of Eth$2 million
- Alleviation of potential drainage problems in Melka Sadi area
- Simplified water control operations
- Unfavorable foundation conditions at the alternative Melka Marer site
2.2 Irrigation System Design
The irrigation layout utilizes:
- A central ridge for the primary supply canal
- Primary drains along eastern and western boundaries
- Secondary canals following contours
- Design duty of 1.68 l/sec/ha (overall irrigation efficiency of 69%)
2.3 Flood Protection
The western dyke is designed to protect against Awash River floods up to 2000 m³/sec:
- Economic analysis suggests optimal dyke height of 3-4 meters
- Clearance of riverside trees could reduce required height by 0.5-1m
- Eastern dyke protects against floods from Alledeghi plain
3. Implementation Strategy
3.1 Contract Structure
Contract Type | Description |
---|---|
Preliminary Works | Bush clearing, site investigations, link road construction |
Buildings and Services | Settlers housing, AVA housing, administration buildings |
Main Works | Barrage construction, canal works, flood protection, etc. |
3.2 Labor Strategy
The report recommends labor-intensive methods where economically competitive:
- Excavation of secondary/tertiary canals by hand
- Construction of minor structures in masonry
- 90% reimbursement of increased labor costs to contractors
3.3 Phased Implementation
The project will be completed in three phases:
- Phase I (by June 1976): 4,200 ha including AVA settlement farm
- Phase II: Adjacent 4,400 ha including existing concessions
- Phase III: Remaining 1,500 ha
4. Key Technical Data
4.1 Water Requirements
Project Area | Gross Area (ha) | Design Flow (cumecs) |
---|---|---|
Melka Sadi | 5,100 | 5.5 |
Amibara | 10,100 | 12.2 |
Bolhamo (potential) | 8,900 | 10.8 |
Angelele (potential) | 4,750 | 5.8 |
4.2 Flood Data
Design floods at Melka Sadi barrage site:
- 1000 cumecs: ~10,000 year return period
- 2000 cumecs: ~50 year return period
5. Appendices Summary
Appendix A: Existing Developments
Describes five existing developments in the project area including the Melka Marer Research Station, AVA settlement farms, and three large concessions.
Appendix B: Single vs. Two Diversion Structures
Detailed cost-benefit analysis favoring a single barrage at Melka Sadi with estimated Eth$2 million savings.
Appendix C: Effects of Angelele/Bolhamo Development
Potential modifications needed if these adjacent areas are developed, including increased canal capacities.
Appendix D: Western Dyke Design
Technical considerations for flood protection dyke alignment and height.
Appendix E: Groundwater Interpretation
Analysis suggesting silty loam subsoil may behave like clay, affecting drainage assumptions.
Appendix F: Contract Types
Detailed specifications for different contract packages including site investigations, link road, bush clearing, etc.
6. Decisions Required from AVA
- Approval of proposed layout with single diversion structure
- Approval of design criteria for irrigation, flood protection, etc.
- Approval of implementation methods and program
- Approval for Eth$20,000 force account expenditure for site access
- Agreement on liaison procedures between AVA and Halcrows
Note: This report represents the preliminary design phase. Detailed designs will follow after AVA approval of these proposals and completion of additional site investigations.