Amibara Drainage Project - Contractor's Claims Preliminary Report
Project Overview
Contract: ADP/T/01/90 - Drainage Works
Contractor: Joint Venture JR-Dynidag
Original Completion Date: 14 April 1994 (30 months from October 1991)
Status as of November 1994: Works ongoing with interim extension to 31 January 1995
Total Claims Value: ~49% of original contract price (DM 2.49M + Birr 14.31M)
Claims Summary
Claim No | Description | Claimed Costs | Claimed EOT | Preliminary Assessment |
---|---|---|---|---|
1 | Late Mobilisation Advance | DM 170,764 + Birr 393,444 | 11 weeks | Likely rejected (no contractual basis) |
2 | Late Customs Clearance | DM 960,708 + Birr 2,907,938 | 23.3 weeks | Partial acceptance (7-10 weeks, reduced costs) |
3 | Withholding Permission to Commence | Birr 59,598 | 5 weeks | Likely rejected (Contractor's default) |
4 | Lack of Possession of Site (Afar disruption) | DM 265,130 + Birr 3,981,779 | 18 weeks | Likely accepted under Clause 65 (special risks) |
5 | Reduced Productivity of Workforce | DM 190,143 + Birr 1,501,474 | nil | Likely rejected (no proper records) |
6 | Care of the Works (Flooding) | DM 79,404 + Birr 619,551 | 9.5 weeks | Partial acceptance (time but likely no costs) |
7 | Unforeseen Conditions at MD1 and SD3 | Birr 1,040,124 | 7 weeks | Likely rejected (Contractor's responsibility) |
8 | Late Changes in Design | DM 877,221 + Birr 3,757,768 | 22.5 weeks | Under investigation (likely minimal acceptance) |
9 | Changes in Cost Legislation | DM -28,902 + Birr 51,309 | 0.5 weeks | Rejected per Employer's legal advice |
10 | Restraining Order on Vehicles | Pending | Pending | Pending clarification |
Key Findings
- Most substantial claims relate to site access issues (Claim 4) and customs delays (Claim 2)
- Engineer questions many claims due to lack of proper notification under Clause 52A procedures
- Significant concurrency issues exist between different delay events
- Contractor's cost calculations require verification (e.g., expatriate rates, office costs)
Preliminary Conclusions
The Engineer's preliminary assessment suggests:
- Likely acceptable costs: ~DM 700,000 + Birr 6 million (significantly less than claimed)
- Likely acceptable extension of time: ~35 weeks (vs 75 weeks claimed)
- Major valid claims relate to special risks (Clause 65) for Afar disruptions and some customs delays
- Many claims fail due to procedural issues (lack of proper notices) or being Contractor's risk
Further detailed analysis required for Claims 4 and 8 before final determinations can be made.
Contractual Principles Applied
The assessment applies key FIDIC 3 (with World Bank modifications) principles:
- Clause 52A: Strict notice requirements for claims (28-day rule)
- Clause 65: Special risks provisions for Afar disruptions
- Clause 20: Exceptional risks for flooding event
- Clause 44: Extension of time considerations
- Concurrency: Overlapping delay events properly considered