Amibara Drainage Project Phase II - Financial Proposal Summary
Project Overview
Client: Transitional Government of Ethiopia, Water Resources Development Authority (WRDA)
Funding Agency: African Development Bank
Consultant: NEDECO (Netherlands Engineering Consultants)
Scope: Detailed designs and tender documents for Phase II of the Amibara Drainage Project, including Project Preparation Report and Environmental Impact Assessment.
Proposal Date: December 1993
Validity: 60 days from submission
Financial Summary
Currency | Amount | Equivalent in NLG |
---|---|---|
Dutch Guilders (NLG) | 637,193 | - |
Ethiopian Birr (ETB) | 370,350 | 777,926 |
Total Project Cost | NLG 777,926 |
Cost Breakdown
1. Personnel Costs
Category | Work Months | Basic Salaries | Overhead | Total |
---|---|---|---|---|
Expatriate Staff | 23.0 | NLG 210,808 | NLG 209,092 (99.19%) | NLG 419,900 |
Local Staff | 17.0 | ETB 79,000 | ETB 94,800 (120%) | ETB 173,800 |
2. Travel & Per Diem
Category | Cost |
---|---|
International Travel (12 trips Amsterdam-Addis) | NLG 46,210 |
Local Per Diem (Expatriates: 700 days @ ETB 140) | ETB 98,000 |
Local Per Diem (Ethiopians: 400 days @ ETB 75) | ETB 30,000 |
3. Equipment & Miscellaneous
- AutoCad Software: NLG 10,100
- Plotter: NLG 4,400
- Survey Crew: ETB 6,400/month (additional requirements)
- Transportation & Materials: NLG 129,093
Payment Schedule
Milestone | Percentage |
---|---|
Contract signing (mobilization) | 20% |
Inception Report submission | 10% |
Pre-design Report acceptance | 10% |
Draft Final Design Report submission | 30% |
Final Design Report acceptance | 10% |
Tender Documents acceptance | 10% |
Project Preparation Report acceptance | 10% |
Key Personnel
Expatriate Team
Name | Position | Monthly Salary (NLG) | Work Months |
---|---|---|---|
Peter Burger | Project Director | 10,937 | 2.0 |
Kuiper | Senior Drainage Engineer | 9,671 | 8.0 |
Van Panhuys | Soil Scientist | 17,909 | 1.0 |
Local Consultants
Name | Position | Monthly Salary (ETB) | Work Months |
---|---|---|---|
Demissie | Project Coordinator | 4,500 | 8.0 |
Desta | Structural Engineer | 5,000 | 1.5 |
Special Conditions
- Tax exemptions for consultants and expatriate staff
- WRDA to provide accommodation (or rental at ETB 3,000/month)
- WRDA to supply office support staff (or at specified rates)
- Exchange rate: 1 ETB = 0.38 NLG
Prepared based on NEDECO's financial proposal dated November 30, 1993