Amibara Drainage Project Consultancy Services Summary
Document: Financial Proposal for Construction Supervision Consultancy Services
Project: Amibara Drainage Project, Stage 1 (Ethiopia)
Consultant: Sir William Halcrow & Partners Limited
Date: July 1988
1. Project Overview
The document presents Halcrow's financial proposal for providing construction supervision consultancy services for the Amibara Drainage Project in Ethiopia's Middle Awash Valley. The proposal was submitted in response to an invitation from the Water Resources Development Authority (WRDA) of Ethiopia dated 21 May 1988.
2. Proposal Structure
The proposal is organized in three volumes:
- Volume 1: Firm's Background
- Volume 2: Approach and Staffing
- Volume 3: Financial Proposal (this document)
3. Financial Summary
Item | Payment Basis | Amount (£ Sterling) | Amount (Birr) |
---|---|---|---|
Expatriate Staff Charges | LS rate | 765,867 | - |
Reimbursable Expenses | Various | 62,080 | 53,200 |
Estimated Total | 827,947 | 53,200 |
Note: Excludes costs for international air travel, office/staff accommodation, equipment, vehicles, local staff, and price escalation.
4. Key Components
4.1 Staff Charges
The proposal includes charges for 13 professional staff members with a total estimated input of 135 man-months over 50 months. Staff charge rates vary by position and location (UK vs. Ethiopia).
4.2 Reimbursable Expenses
Major expense categories include:
- Mobilization (£8,400)
- Personal Effects Baggage (£10,350)
- Airfreight of Equipment (£17,830)
- Staff Accommodation & Subsistence (Birr 53,200)
- Communications (£15,000)
- Laboratory Tests (£5,000)
5. Contract Terms
The document includes draft contract terms based on the International General Rules of Agreement (IGRA - 1979 D&S), covering:
- Scope of services and relationship between parties
- Commencement, completion, and termination conditions
- Rights and duties of the consulting engineer
- Liability limitations (capped at total estimated man-month charges)
- Client obligations including data provision and visa assistance
- Dispute resolution through ICC arbitration in Addis Ababa
- Payment terms including 20% advance payment
6. Key Conditions
- Services duration: 50 months
- Consultant's liability expires 6 years after completion
- Language: English (ruling language)
- Governing law: Ethiopian
- Payments in £ Sterling and Ethiopian Birr
- Interest on late payments at National Bank of Ethiopia rate
7. Appendices
The document includes three key appendices:
- Appendix A: Scope of Services (Construction Supervision)
- Appendix B: Assigned Specialists and Facilities (to be finalized)
- Appendix C: Remuneration and Payment terms