Ministry of Water Resources | Addis Ababa, April 1997
This document presents a comprehensive review of contractor claims for the Amibara Drainage Project 1, originally submitted in September 1994. The claims were assessed by a committee following specific contractual guidelines, with recommendations for approval or rejection of each claim item.
General information about the contract including parties, prices, and key dates. Accepted as factual records by the committee.
Contractor withdrew this claim. Committee reviewed and found no substantial hindrance to mobilization.
Major claims regarding delays in customs clearance:
Claims related to disruptions by Afar people:
Most claims rejected except for:
Accepted that securing site was employer's responsibility. Recommended payment of Birr 381,279.30.
Recommended payments for:
Employer counter claims totaling Birr 375,996.98 for flooding of fields were accepted.
Committee accepted 36.5 days extension (to May 7, 1994) vs. Resident Engineer's recommendation extending to February 17, 1995.