Amibara Drainage Project Phase II - Summary
Project Overview
The document presents a financial proposal from NEDECO (Netherlands Engineering Consultants) for consulting services on Phase II of the Amibara Drainage Project in Ethiopia, commissioned by the Water Resources Development Authority with funding from the African Development Bank.
Key Details:
- Date: December 1993
- Services: Detailed designs, tender documents, project preparation report, and environmental impact assessment
- Validity: 60 days from proposal submission
Financial Proposal Highlights
Cost Summary
Item | Total (NLG) | Total (ETB) |
---|---|---|
Home Office Salaries & Overhead | 419,900 | 173,800 |
Travel and Per Diem | 46,210 | 128,000 |
Transportation & Equipment | 129,093 | 42,480 |
Total Cost | 726,029 | 370,350 |
Profit | 41,990 | 26,070 |
Grand Total | 777,926 | 396,420 |
Exchange rate: ETB 1 = NLG 0.38
Payment Schedule
- 20% at contract signing (mobilization)
- 10% upon Inception Report submission
- 10% upon Pre-design Report acceptance
- 30% upon Draft Final Design Report
- 10% upon Final Design Report acceptance
- 10% upon Tender Documents acceptance
- 10% upon Project Preparation Report acceptance
Key Personnel
Expatriate Staff
Position | Months | Monthly Salary (NLG) |
---|---|---|
Project Director | 2.0 | 10,937 |
Team Leader/Drainage Engineer | 8.0 | 9,671 |
Soil Scientist | 1.0 | 17,909 |
Hydraulic Engineer | 1.0 | 11,444 |
Local Staff
Position | Months | Monthly Salary (ETB) |
---|---|---|
Project Coordinator | 8.0 | 4,500 |
Structural Engineer | 1.5 | 5,000 |
Irrigation Agronomist | 2.0 | 5,000 |
Special Conditions
- Tax exemptions for consultants and imported equipment
- Option for AutoCad design (additional NLG 14,500)
- Assumption of WRDA-provided office support and accommodation
- Survey crew available at ETB 6,400/month if needed
Declaration
Peter Burger, Project Director of DHV Consultants BV, representing NEDECO, accepted the proposed contract format on November 30, 1993.