×

Summery

Aleltu Hydroelectric Project Summary

Aleltu Hydroelectric Project Summary

Project Overview

The Aleltu Hydroelectric Project is a major hydroelectric development study conducted for the Ethiopian Electric Light and Power Authority (EELPA) by Acres International Limited in 1984. The project is located about 80 km north of Addis Ababa.

Key Findings: The study concluded that the first stage development (300 MW) is technically and economically very attractive, with an ultimate development potential of about 1,020 MW from 12 subbasins.

Project Components

  • Stage I Development: Tiliku Aleltu (3×50 MW) and Jida (3×50 MW) schemes
  • Power Generation: 1,040 GW·h/yr of firm energy
  • Head: Approximately 1,100 m
  • Reservoirs: Tiliku Aleltu (92 Mm³) and Jida (990 Mm³ live storage)
  • Powerhouse: Located in Zega Wedem Gorge

Economic Analysis

Metric Value
Total Construction Cost (1984) US $407 million
Unit Cost of Capacity US $1,357/kW
Unit Cost of Firm Energy 47.1 mills/kW·h
Comparison with Gilgel Gibe 35% lower unit costs

Key Recommendations

  1. Proceed with feasibility study for first stage development (Tiliku Aleltu and Jida)
  2. Install additional streamflow and rainfall recording stations
  3. Continue data recording at existing meteorological stations
  4. Obtain 1:50,000-scale mapping of entire project area
  5. Investigate reservoir integrity at Tiliku Aleltu and Jida sites

Project Timeline

If studies began before end of 1984, first units could be online by January 1993. Construction would take approximately 5.25 years from commitment to first unit online.

Environmental and Social Considerations

The study found no significant environmental or social factors that should prevent implementation, though about 500-600 farming families would be affected by reservoir creation. Rehabilitation programs were considered including land redistribution and resettlement options.

Ultimate Development Potential

The ultimate development would include 12 subbasins with total installed capacity of 1,023 MW and firm energy generation of 3,592 GW·h/yr. Future stages would include Weserbi, Gomoro, Robi, Chacha, Duber, Robi-Gomoro, Jinjer, and Sibilu developments.