×

Summery

Aleltu Hydroelectric Project Summary

Aleltu Hydroelectric Project - Executive Summary

Project Overview

Location: Approximately 60 km north of Addis Ababa, Ethiopia

Study Date: June 1984

Conducted by: Acres International Limited for Ethiopian Electric Light and Power Authority (EELPA)

Financing: Jointly funded by Canadian International Development Agency (CIDA) and EELPA

Key Findings

Reconnaissance Study

  • Identified 14 subbasins with theoretical potential of 3,800 GW·h/yr
  • Economic potential: 3,600 GW·h/yr from 12 subbasins (1,020 MW at 40% load factor)
  • Recommended staged development concept with interconnected reservoirs

Prefeasibility Study (First Stage)

  • Recommended first stage: Tiliku Aleltu (300 MW) followed by Jida development
  • Generation potential: 1,040 GW·h/yr firm energy
  • Estimated construction cost: $407 million (1984 dollars)
  • Unit cost: $1,357/kW capacity, 47.1 mills/kW·h energy
  • 35% lower unit costs compared to Gilgel Gibe alternative

Project Components

Component Description
Tiliku Aleltu Dam Earth- and rock-fill dam (54m height), 92 Mm³ reservoir
Jida Dam Earth- and rock-fill dam (65m height), provides 90% of Stage I storage
Power Tunnel Concrete-lined, 16.3 km length
Powerhouse 6×50 MW units, located in Zega Wedem Gorge
Transmission 230 kV line to Addis Ababa

Implementation Schedule

  • Feasibility study recommended to start by end of 1984
  • First units could be online by January 1993
  • Construction duration: 5.25 years from commitment to first unit

Recommendations

  1. Proceed with feasibility study for first stage development
  2. Install additional streamflow and rainfall recording stations
  3. Continue data recording at existing stations
  4. Obtain 1:50,000-scale mapping of project area
  5. Confirm reservoir integrity at dam sites

Economic Analysis

The project compares favorably with alternatives, showing:

  • 35% lower unit costs than Gilgel Gibe
  • Favorable location near Addis Ababa
  • Staged development potential matching load growth

Environmental & Social Considerations

  • 500-600 families potentially affected by reservoir creation
  • Most homes located on ridges will not be flooded
  • Rehabilitation programs considered for affected farmers
  • No major environmental barriers identified