Aleltu Hydroelectric Project - Executive Summary
Project Overview
Location: Approximately 60 km north of Addis Ababa, Ethiopia
Study Date: June 1984
Conducted by: Acres International Limited for Ethiopian Electric Light and Power Authority (EELPA)
Financing: Jointly funded by Canadian International Development Agency (CIDA) and EELPA
Key Findings
Reconnaissance Study
- Identified 14 subbasins with theoretical potential of 3,800 GW·h/yr
- Economic potential: 3,600 GW·h/yr from 12 subbasins (1,020 MW at 40% load factor)
- Recommended staged development concept with interconnected reservoirs
Prefeasibility Study (First Stage)
- Recommended first stage: Tiliku Aleltu (300 MW) followed by Jida development
- Generation potential: 1,040 GW·h/yr firm energy
- Estimated construction cost: $407 million (1984 dollars)
- Unit cost: $1,357/kW capacity, 47.1 mills/kW·h energy
- 35% lower unit costs compared to Gilgel Gibe alternative
Project Components
Component | Description |
---|---|
Tiliku Aleltu Dam | Earth- and rock-fill dam (54m height), 92 Mm³ reservoir |
Jida Dam | Earth- and rock-fill dam (65m height), provides 90% of Stage I storage |
Power Tunnel | Concrete-lined, 16.3 km length |
Powerhouse | 6×50 MW units, located in Zega Wedem Gorge |
Transmission | 230 kV line to Addis Ababa |
Implementation Schedule
- Feasibility study recommended to start by end of 1984
- First units could be online by January 1993
- Construction duration: 5.25 years from commitment to first unit
Recommendations
- Proceed with feasibility study for first stage development
- Install additional streamflow and rainfall recording stations
- Continue data recording at existing stations
- Obtain 1:50,000-scale mapping of project area
- Confirm reservoir integrity at dam sites
Economic Analysis
The project compares favorably with alternatives, showing:
- 35% lower unit costs than Gilgel Gibe
- Favorable location near Addis Ababa
- Staged development potential matching load growth
Environmental & Social Considerations
- 500-600 families potentially affected by reservoir creation
- Most homes located on ridges will not be flooded
- Rehabilitation programs considered for affected farmers
- No major environmental barriers identified