Aleltu Hydroelectric Project - Reconnaissance and Prefeasibility Studies
Project Overview
The Aleltu Hydroelectric Project is located about 80 km north of Addis Ababa, Ethiopia. The study was conducted by Acres International Limited in collaboration with the Ethiopian Electric Light and Power Authority (EELPA) between 1983-1984.
Key Project Data
Parameter | Ultimate Project | First Stage (Tiliku Aleltu & Jida) |
---|---|---|
Drainage Area | 4,230 km² (12 subbasins) | 1,207 km² (combined) |
Average Annual Runoff | 49 m³/s | 13.8 m³/s (combined) |
Gross Head | 1,070 m | 1,070 m |
Firm Energy Potential | 3,592 GW·h/yr | 1,040 GW·h/yr (combined) |
Installed Capacity (40% plant factor) | 1,023 MW | 300 MW (combined) |
Project Components
First Stage Development
The recommended first stage includes:
- Tiliku Aleltu Development
- Earth-and-rock-fill dam (54m high)
- Reservoir with 92 Mm³ storage at FSL 2,598.5m
- 60% regulation of inflow (5.6 m³/s average)
- Jida Development
- Earth-and-rock-fill dam (65m high)
- Reservoir with 1,050 Mm³ storage at same FSL
- 100% regulation of inflow (8.2 m³/s average)
- Interconnection: 800m unlined tunnel between reservoirs
- Power Conveyance:
- 16.3 km concrete-lined horseshoe tunnel (3.2m diameter)
- 2.1 km steel surface penstock (2.4m diameter)
- Powerhouse:
- Surface powerhouse with 6 Pelton units (51 MW each)
- Total installed capacity: 300 MW
- Firm energy: 1,040 GW·h/yr
Key Findings
Reconnaissance Study Results
- Identified 14 subbasins with hydroelectric potential
- Recommended staged development approach
- Tiliku Aleltu and Jida schemes selected as most economic first stage
- Powerhouse Location A in Zega Wedem Gorge identified as optimal
Prefeasibility Study Results
- Confirmed technical feasibility of first stage
- Hydrologic analysis showed:
- Mean annual rainfall: 1,188 mm (Tiliku Aleltu), 1,103 mm (Jida)
- 1:10,000-year flood peaks: 232 m³/s (Tiliku Aleltu), 329 m³/s (Jida)
- Geological conditions generally favorable for construction
- Estimated construction period: Approximately 5 years
Economic Analysis
- Compared against long-term ICS grid energy supply cost of 35 mills/kW·h
- First stage average energy cost: 25.6 mills/kW·h
- Benefit/Cost ratio: 1.37 for first stage
- Incremental energy costs for future stages below grid supply cost
Recommendations
- Proceed with feasibility study of first stage development
- Install additional streamflow and rainfall recording stations
- Ensure continuous recordings at existing meteorological stations
- Obtain 1:50,000-scale mapping of entire project area
Conclusion: The first stage development of Aleltu (300 MW) is technically and economically very attractive at the prefeasibility study level. The ultimate development could reach 1,020 MW through staged development of 12 subbasins.