Emergency Ground Water Development Project (Akaki) Summary

Emergency Ground Water Development Project (Akaki)

Contract No. I: Civil Works - Bill of Quantities

Project Overview

Client: Transitional Government of Ethiopia - Addis Ababa Water and Sewerage Authority (AAWSA)

Consultant: Water Supply and Sewerage Agency (WSSA) with sub-consultant Metaferia Consulting Engineers (MCE)

Date: December 1994

Project Components: Well field development, reservoirs, pump houses, transmission pipelines, and distribution systems

Project Components Summary

Bill No. Description Pages
11 General Items 2
12 Well Field Area D: Collector & Transfer 22
13 Collecting Tank (CT) 47
14 Ground Water Site 1 (GW1) 39
15 Ground Water Site 2 (GW2) 39
16 Ground Water Site 3 (GW3) 38
17 Ground Water Site 4 (GW4) 15
18 Transmission Pipeline 19
19 Distribution System (S2) 11

Key Project Elements

Well Field Area D (Bill No. 12)

  • Access road construction (63,120 m² stripping, 5,900 m³ excavation)
  • Construction of 15 well heads
  • Collector and transfer pipe laying (various diameters from DN250 to DN500)
  • Generator houses for three substations

Collecting Tank (CT - Bill No. 13)

  • 1,000 m³ capacity reservoir
  • Pump house with concrete works and electrical installations
  • Operation building & chlorine cylinder shed
  • Generator house, operator's dwelling, and guard house
  • Drainage and foul water disposal system

Ground Water Sites (GW1-GW4)

  • GW1: 1,000 m³ reservoir
  • GW2 and GW3: 2,500 m³ reservoirs each
  • GW4: 2,500 m³ reservoir (simpler configuration)
  • Each site includes pump houses, generator houses, operator dwellings, and guard houses

Transmission Pipeline (Bill No. 18)

  • Four portions: CT-GW1, GW1-GW2, GW2-GW3, GW3-GW4
  • Various pipe diameters with associated excavation and installation works

Distribution System (Bill No. 19)

  • Pipe laying for water distribution network

Construction Details

The document provides detailed quantities and specifications for:

  • Earthworks (excavation, backfilling, compaction)
  • Concrete works (foundations, walls, slabs, columns)
  • Reinforcement steel (various diameters from 6mm to 20mm)
  • Pipe laying (DCI pipes from DN250 to DN500)
  • Structural works (roofing, masonry, finishes)
  • Electrical installations (distribution boards, lighting, power sockets)
  • Mechanical installations (valves, fittings, water meters)

Project Organization

The document is organized as a detailed Bill of Quantities with:

  • Item numbers and descriptions
  • Units of measurement
  • Quantities
  • Unit rates (to be filled by tenderers)
  • Amount columns (to be filled by tenderers)

All amounts are to be provided in Ethiopian Birr (BIRR) and Foreign Currency (FC).