×

Summery

Emergency Ground Water Development Project (Akaki) - Summary

Emergency Ground Water Development Project (Akaki) - Summary

Project Overview

The Emergency Ground Water Development Project (Akaki) is a water supply initiative for Addis Ababa, Ethiopia, designed to address critical water shortages in the city. The project involves developing groundwater resources from the Akaki well field to deliver approximately 52,000 m³/day of water.

Parties Involved

Client

Addis Ababa Water and Sewerage Authority (AAWSA)

Consultant

Water Supply and Sewerage Agency (WSSA) with Sub-Consultant Metaferia Consulting Engineers (MCE)

Contract Details

Contract Type Consultancy Services for Contract Administration and Construction Supervision
Effective Date Upon signature (January 1995)
Duration 30 months (24 months construction + 6 months tendering)
Budget Ceiling US$267,300 (foreign currency) + Birr 8,960,490 (local currency)

Scope of Services

Main Responsibilities

  • Tender evaluation and contract award recommendations
  • Preparation and review of working drawings
  • Construction supervision and contract management
  • Inspection and testing of equipment
  • Quality control and work progress monitoring
  • Commissioning of the waterworks
  • Preparation of "as-built" drawings
  • Training and technology transfer

Project Components

  • 4 pumping stations
  • 5 reservoirs (2×1000m³ + 3×2500m³)
  • Auxiliary structures (buildings, guard house, etc.)
  • 56km of pipelines (collector, transmission, distribution)
  • Steel bridge for Akaki River crossing
  • Electro-mechanical equipment

Key Personnel

Position Name Key Qualifications
Project Director Ato Mesfin Tegene Overall project leadership
Project Engineer Ato Goitom K/Giorgis Water supply engineering, MSc in Water Supply & Sanitation
Senior Water Supply Engineers Ato Gezahegn Wolde, Ato Ashenafi Kibret, Ato Amhayesus Metaferia Extensive experience in water projects, some with international experience
Specialists Various (Structural, Electrical, Mechanical, Hydrogeologist, etc.) Specialized technical expertise in respective fields
Site Engineers 3 engineers Construction supervision experience

Payment Terms

  • 20% advance payment (US$47,600 + Birr 1,792,092)
  • Monthly billing with 60-day payment terms
  • Escalation clause: 6% annual adjustment for cost increases
  • Interest of 12% per annum on late payments

Contractual Provisions

Key Clauses

  • Force Majeure: Defined broadly with provisions for extension of time and payment during such events
  • Termination: Either party may terminate under specified conditions with 30-60 days notice
  • Confidentiality: 2-year obligation after contract expiration
  • Dispute Resolution: Amicable settlement preferred, with arbitration as final recourse
  • Tax Exemptions: Provided for foreign personnel and equipment

Appendices Summary

Appendix Content
A Detailed Scope of Consultancy Services
B Services and Facilities provided by Consultant
C Services and Facilities provided by Client
D Work Programme and Schedule
E Remuneration Details and Cost Breakdown
F Key Personnel CVs (extensive technical backgrounds)
G Terms of Reference